Vietnam: Leading the Nuclear Charge – Vietnam's Quest to Develop Nuclear Power
Last Updated: 2 March 2012

By Pham Nghiem Xuan Bac & Luu Tien Ngoc

Malaysia announced in December 2010 that it intends to build two nuclear power plants by 2022 and Indonesia has also indicated its intention to explore nuclear energy as a means of addressing its energy shortfall. However, it is Vietnam which, in a number of ways, is leading the pack in the South East Asia region in its drive to develop nuclear power plants.

Introduction

The Vietnamese government has been working for a number of years now towards achieving its stated desire to develop nuclear power for peaceful purposes based on modern, verified technology. The race to generate nuclear energy is driven largely by the country's growing energy demand which, according to government projections, is expected to increase by 16 per cent per year until 2015.

One of the key challenges which Vietnam faces is that currently at least a third of its energy is generated by hydropower plants but there are two key issues which threaten the viability of hydropower as a long term solution to Vietnam's energy needs.

Firstly, hydropower projects depend on favourable weather conditions and in recent periods of drought, the existing hydropower projects have struggled to generate sufficient output to meet peak demand and this situation will only worsen as the demand increases. Secondly, other than the major new plant at Son La, very few sites have been identified as being suitable for additional large scale hydropower projects.

Therefore, Vietnam has had to look to an alternative renewable source to meet its growing demand. Vietnam has announced its intention to construct at least 13 nuclear power turbine units in Vietnam in the next 20 years with the aim that, by 2030 these nuclear power units will provide 15,000-16,000MW of power representing 10 per cent of the total installed capacity in Vietnam.

Creating a legal and regulatory framework

Vietnam has been developing its policy on nuclear power generation for many years, demonstrated by the establishment of the Vietnam Atomic Energy Commission (now the Vietnam Atomic Energy Institute) in 1976 and more recently, the issuance by the Prime Minister in January 2006 of the Strategy for Peaceful Use of Atomic Energy up to 2020 and the corresponding Master Plan issued in 2007.

However, only in the last couple of years has the government started to build a legislative framework for the implementation of nuclear power projects from design to decommissioning and fuel supply to storage and ultimately, the safe disposal of nuclear waste.

However, given the rigorous nature of international regulation and the policy considerations surrounding the implementation of nuclear power projects, it has yet to be seen whether the existing and currently anticipated legislation will go far enough in order to enable Vietnam to fulfil its nuclear vision on schedule.

The main piece of legislation which underpins Vietnam's framework of atomic energy regulation is the Law on Atomic Energy which was promulgated on 3 June 2008 and came into effect on 1 January 2009. This law sets out comprehensive high level principles which govern Vietnam's pursuit of nuclear power and the focus is, unsurprisingly, on ensuring safety of persons and the environment and the need to utilize modern proven technology, together with emphasizing non-proliferation.

The Law on Atomic Energy has since been followed by three Decrees and a number of Decisions of the Prime Minister which start to elaborate on some of the detail as to how Vietnam intends to address the various complex issues which surround the implementation of its atomic energy strategy.

Ambitious timetable for implementation

The roadmap for the future development of nuclear energy in Vietnam over the next twenty years is set out in the Prime Minister's Decision 906 dated 17 June 2010. According to Decision 906, the first nuclear plant, Ninh Thuan 1, with a capacity of approximately 2000MW, is scheduled to commence construction in 2015 subject to the requisite regulatory consents and frameworks being in place and necessary feasibility studies having been carried out. It is anticipated that commercial operation will commence in 2020 with further capacity scheduled to come on line in 2021.

The project is to be located in the Phuoc Dinh commune, Thuan Nam district of the Ninh Thuan province.

A second nuclear power plant (Ninh Thuan 2) comprising a further 2 x 1,000 MW turbines is then also slated for development in Ninh Thuan province but in the Vinh Hai commune, Ninh Hai district with construction due to commence by 2020.

EVN, the state electricity utility in Vietnam, will invest in and ultimately be the operator of the initial two projects. Subsequently, it is envisaged that domestic economic joint ventures may be allowed to develop the remaining nuclear power plants provided they have the requisite capabilities, skill and experience to be awarded a nuclear operating licence.

It is not clear from Decision 906 whether there will be opportunities for foreign investors to be involved in these future plants in joint venture with a local partner but the Decision does not preclude the possibility. Therefore, Vietnam has elucidated an ambitious plan to develop nuclear power over the couple of decades but there are a number of factors which may yet hinder Vietnam's progress in achieving its stated goals.

Potential challenges which face the development of nuclear power in Vietnam

  • Lack of a centralised Nuclear Energy Programme Implementation Organisation

    The Government of Vietnam opted not to form a separate Nuclear Energy Programme Implementation Organisation (NEPIO) and empower the NEPIO to formulate all the required strategic and regulatory requirements to progress implementation of its nuclear power programme. Instead, each relevant government ministry, including the Ministry of Industry and Trade, the Ministry of Natural Resources and Environment, the Ministry of Construction, the Ministry of Health, the Ministry of Agriculture and Rural Development and the Ministry of Science and Technology, remains responsible for duties assigned to it under the Law on Atomic Energy.

    In addition, there are a number of different agencies and taskforces charged by the ministries to prepare plans and strategies in connection with the promulgation of nuclear power such as the Vietnam Atomic Energy Agency (formed by the Ministry of Science and Technology through its regulation dated 31 August 2010), the Vietnam Atomic Energy Institute and the Vietnam Agency for Radiation and Nuclear Safety & Control (established by the Ministry of Science and Technology in 2004).

    IAEA recommends that a NEPIO which reports directly to government oversees the implementation of a national nuclear programme for a variety of reasons. The disadvantage of splitting the function across a number of ministries and agencies is that there may be a lack of coordination between each of the various agencies and ministries and insufficient knowledge at all levels of each ministry or agency regarding the international norms and political and socio-economic issues that surround the development of nuclear policy to enable a cohesive and consistent approach.

  • Liability for Nuclear Damage

    Vietnam has not signed the Vienna Convention on Civil Liability for Nuclear Damage 1963 (the Vienna Convention). The Vienna Convention channels liability for third party personal injury and death and third party property damage caused by a nuclear incident to the operator of a nuclear facility. The operator is obliged to maintain insurance or some other financial security to meet this liability. The importance of these channelling provisions should not be underestimated in terms of the ability of the party to the Vienna Convention to access the nuclear insurance market.

    As an alternative, some countries such as the United-States have in place domestic legislation which channels liability in the same way, such as the United-States' Price Anderson Act (Atomic Energy Act 1954) which also enables access to the insurance market.

    The Vienna Convention sets a minimum level of limit of liability on the operator in respect of nuclear damage - under the original convention the limit cannot be less than US$ 5 million but in 1997, an amending protocol to Vienna Convention extended liability of the operator to matters such as environmental damage and increased the minimum limit of liability of the operator to 300 million SDR (roughly equivalent to US$ 400 million).

    However, the actual limit of liability is set by the domestic legislation which implements the convention. The limit on liability of 150 million SDR under the Law on Atomic Energy (Article 88) falls short of the Vienna Convention. Vietnam may gain more acceptance of its nuclear ambitions in the international market if it increases these limits to comply with the Vienna Convention.

  • Prohibitive cost and limited financing options

    On a short term view, one of the major disadvantages of atomic energy is the huge upfront investment required to put in place the necessary regulatory framework and build the necessary resources and knowledge pool to sustain a nuclear power industry.

    In addition, the lengthy construction period associated with a nuclear power plant and need to import sophisticated modern nuclear technology is prohibitively expensive compared with the cost of procuring a traditional coal fired plant, even though the costs of operating a nuclear plant are low, by comparison with other technologies. The cost of developing the first nuclear power plant in Vietnam is considered to be at least US$ 10 billion - significantly more than the cost of developing a coal fired plant.

    As a result, Vietnam will almost certainly be heavily reliant on export credit agencies and commercial debt to provide financial support to its early nuclear projects. As yet, no nuclear project has secured financing in the international commercial debt market on a project finance basis. Vietnam's ultimate goal is to foster the expertise and experience to potentially develop its own technology and build its nuclear operating and fuel processing capability within Vietnam to reduce cost in the long term but this will take a number of years to achieve.

  • Security of Fuel Supply

    Vietnam will need to import uranium to process into fuel assemblies for use in its nuclear power plants. However, this leaves Vietnam somewhat at the mercy of the uranium import price which can be unpredictable. It is thought that Vietnam may have its own reserves of uranium ore but there is a question mark as to whether the quality of its reserves are sufficient for the purpose of nuclear fuel. Vietnam has reportedly signed an agreement with a Canadian mining company to carry out an assessment of Vietnam's potential for mining uranium ore, including the economic and technical feasibility of any reserves found.

    It remains to be seen whether Vietnam can defray the cost of operating its nuclear power plants by utilizing its own uranium reserves or whether it will continue to need to rely on importing uranium from other countries at potentially considerable cost.

  • Developing manpower and technology

    The Government of Vietnam is acutely aware of the need to promote training of qualified persons to operate the plants and ultimately to take over the design, manufacture and construction of these plants instead of using foreign labour and equipment to drive down cost and boost the Vietnamese economy.

    Decree 07 dated 25 January 2010 contains a number of measures to attract people to work in the nuclear sector in Vietnam by offering preferential working conditions and an allowance of up to 70% of the rank or grade salaries. The Decree also targets the future workforce in Vietnam by offering scholarships and tuition paid for those studying atomic energy with additional incentives and possible support or overseas study.

    More recently, the Prime Minister has also underlined the importance of training and resourcing in preparation for operation and maintenance of the Ninh Thuan nuclear power plant through Decision 1558 which was issued on 18 August 2010 and the allocation of a budget of around US$ 154 million between now and 2020 for this purpose. The Decision again focuses on offering tertiary education on nuclear sciences at the major universities and training qualified persons overseas to ensure the requisite levels of expertise and experience.

    Even with these measures in place, Vietnam is, to an extent, playing catch up with those countries with an established track record in nuclear power generation. The relevant authorities in Vietnam, including EVN as the proposed operator of the first two projects, will need to ramp up its efforts to be in a position to resource its nuclear activities on such a large scale in the next twenty years and in order to satisfy international requirements regarding operators of nuclear facilities to ensure safety and security.

  • International Co-operation and Assistance

    In the face of such challenges, however, Vietnam is not without support in seeking to further its nuclear power capability. Japan, the United-States, Russia and China, in particular, are all vying to export their technology and credentials to help Vietnam pursue its nuclear plants.

    Vietnam is reported to have signed a formal accord with Russia for the development of the first nuclear power plant, Ninh Thuan 1, using 1200 MWe VVER pressurized water reactors and will supply nuclear fuel for the plant and then remove used fuel for reprocessing. Separately, the Vietnamese Prime Minister has been quoted as saying that Vietnam will partner with Japan to build a second nuclear plant and conduct rare-earth investigation, exploration and processing in Vietnam. China, meanwhile, has also signed a memorandum of understanding with the Vietnam Atomic Energy Commission for cooperation in the nuclear power sector.

    In addition, the French Development Agency has pledged to support Vietnam's nuclear endeavours and Vietnam has met with senior representatives of AREVA to discuss its experiences in building and operating nuclear power plants and AREVA's capability in providing fuel rods, converting and enriching uranium and reprocessing and handling nuclear waste. Vietnam is also reported to have entered into nuclear cooperation agreements with India, South Korea, Canada and Argentina.

    Vietnam also signed a memorandum of understanding with the US government back in 2001 but talks have been accelerated in recent months possibly as a result of the advanced nature of discussions between Vietnam and Russia and China, resulting in a new memorandum of understanding between the US and Vietnam in March 2010.

    This latest memorandum of understanding provides for broad co-operation between the countries on nuclear power including access to nuclear fuel with the ultimate aim of signing a Section 123 agreement to enable US entities like Westinghouse to export their technology.

    However, the latest round of talks between the US and Vietnam have been surrounded in controversy on the basis that the deal struck between the countries allows Vietnam to produce its own nuclear fuel whereas recently in similar agreements with other nations, the US has insisted on including non-proliferation provisions restricting the right for that country to independently enrich uranium.

Conclusion

Given the finite nature of traditional energy sources such as coal and gas and the concerns regarding the viability of large scale hydropower projects to continue to meet Vietnam's ever-increasing demand for power, Vietnam may have little other option than to heavily invest now in a nuclear programme.

However, to implement a successful nuclear power industry in Vietnam going forward, the Vietnamese government will need to ensure that there is a sufficiently detailed and rigorous regulatory regime in place to provide adequate safeguards against the potentially devastating consequences of improper handling of nuclear materials or a nuclear incident which could jeopardize the future of nuclear power as an alternative energy source in Vietnam but also further afield.

This process is already under way with the recent Decrees and Decisions emanating from the National Assembly and the Prime Minister as well as the various ministries and agencies, but there is still more to do if Vietnam is to meet its challenging timetable of having a nuclear power plant operational by 2020.

Despite the challenges, there is little doubt that, where some of its rivals in the region are still grappling with the socio-economic, political and regulatory framework issues that surround the implementation of nuclear power as a viable alternative to traditional energy, Vietnam has embraced nuclear energy as an answer to its growing energy demands and is moving closer to realizing its nuclear ambitions.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

To print this article, all you need is to be registered on Mondaq.com.

Click to Login as an existing user or Register so you can print this article.

More Popular Related Articles on Energy and Natural Resources from Asia Pacific
This publication brings together a brief summary of information on recently completed deals and relevant regulatory updates.
A contentious debate has arisen about whether compensation for landowner time should or ought to be paid.
The average intensity of greenhouse emissions from the National Electricity Market has reduced by about 5% year on year.
Where a proposed mining development has clear environmental impacts, mitigation measures must deal with those impacts.
The Government will now allow the development of a commercial oil shale industry, under strict environmental conditions.
A brief summary of information on deals, market rumours and potential opportunities, and relevant regulatory updates.
Queensland proposes to consolidate five resources Acts into one legislative framework - the 'Common Resources Act'.
Industry bodies have taken an opportunity to highlight regulatory interference as a key barrier to exploration investment.
 
Some comments from our readers…
“The articles are extremely timely and highly applicable”
“I often find critical information not available elsewhere”
“As in-house counsel, Mondaq’s service is of great value”

Tools
Print
Font Size:
Translation
Channels
Mondaq on Twitter
 
Register for Access and our Free Biweekly Alert
Email Address
Company Name
Password
Confirm Password
Mondaq Topics -- Select your Interests
Accounting and Audit
Anti-trust/Competition Law
Consumer Protection
Corporate/Commercial Law
Criminal Law
Employment and HR
Energy and Natural Resources
Environment
Family and Matrimonial
Finance and Banking
Food, Drugs, Healthcare, Life Sciences
Government, Public Sector
Immigration
Insolvency/Bankruptcy, Re-structuring
Insurance
Intellectual Property
International Law
Litigation, Mediation & Arbitration
Media, Telecoms, IT, Entertainment
Privacy
Real Estate and Construction
Strategy
Tax
Transport
Wealth Management
Regions
Africa
Asia
Asia Pacific
Australasia
Canada
Caribbean
Europe
European Union
Latin America
Middle East
U.K.
United States
Worldwide Updates

Terms & Conditions and Privacy Statement

Mondaq.com (the Website) is owned and managed by Mondaq Ltd and as a user you are granted a non-exclusive, revocable license to access the Website under its terms and conditions of use. Your use of the Website constitutes your agreement to the following terms and conditions of use. Mondaq Ltd may terminate your use of the Website if you are in breach of these terms and conditions or if Mondaq Ltd decides to terminate your license of use for whatever reason.

Use of www.mondaq.com

You may use the Website but are required to register as a user if you wish to read the full text of the content and articles available (the Content). You may not modify, publish, transmit, transfer or sell, reproduce, create derivative works from, distribute, perform, link, display, or in any way exploit any of the Content, in whole or in part, except as expressly permitted in these terms & conditions or with the prior written consent of Mondaq Ltd. You may not use electronic or other means to extract details or information about Mondaq.com’s content, users or contributors in order to offer them any services or products which compete directly or indirectly with Mondaq Ltd’s services and products.

Disclaimer

Mondaq Ltd and/or its respective suppliers make no representations about the suitability of the information contained in the documents and related graphics published on this server for any purpose. All such documents and related graphics are provided "as is" without warranty of any kind. Mondaq Ltd and/or its respective suppliers hereby disclaim all warranties and conditions with regard to this information, including all implied warranties and conditions of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Mondaq Ltd and/or its respective suppliers be liable for any special, indirect or consequential damages or any damages whatsoever resulting from loss of use, data or profits, whether in an action of contract, negligence or other tortious action, arising out of or in connection with the use or performance of information available from this server.

The documents and related graphics published on this server could include technical inaccuracies or typographical errors. Changes are periodically added to the information herein. Mondaq Ltd and/or its respective suppliers may make improvements and/or changes in the product(s) and/or the program(s) described herein at any time.

Registration

Mondaq Ltd requires you to register and provide information that personally identifies you, including what sort of information you are interested in, for three primary purposes:

  • To allow you to personalize the Mondaq websites you are visiting.
  • To enable features such as password reminder, newsletter alerts, email a colleague, and linking from Mondaq (and its affiliate sites) to your website.
  • To produce demographic feedback for our information providers who provide information free for your use.

Mondaq (and its affiliate sites) do not sell or provide your details to third parties other than information providers. The reason we provide our information providers with this information is so that they can measure the response their articles are receiving and provide you with information about their products and services.

If you do not want us to provide your name and email address you may opt out by clicking here .

If you do not wish to receive any future announcements of products and services offered by Mondaq by clicking here .

Information Collection and Use

We require site users to register with Mondaq (and its affiliate sites) to view the free information on the site. We also collect information from our users at several different points on the websites: this is so that we can customise the sites according to individual usage, provide 'session-aware' functionality, and ensure that content is acquired and developed appropriately. This gives us an overall picture of our user profiles, which in turn shows to our Editorial Contributors the type of person they are reaching by posting articles on Mondaq (and its affiliate sites) – meaning more free content for registered users.

We are only able to provide the material on the Mondaq (and its affiliate sites) site free to site visitors because we can pass on information about the pages that users are viewing and the personal information users provide to us (e.g. email addresses) to reputable contributing firms such as law firms who author those pages. We do not sell or rent information to anyone else other than the authors of those pages, who may change from time to time. Should you wish us not to disclose your details to any of these parties, please tick the box above or tick the box marked "Opt out of Registration Information Disclosure" on the Your Profile page. We and our author organisations may only contact you via email or other means if you allow us to do so. Users can opt out of contact when they register on the site, or send an email to unsubscribe@mondaq.com with “no disclosure” in the subject heading

Mondaq News Alerts

In order to receive Mondaq News Alerts, users have to complete a separate registration form. This is a personalised service where users choose regions and topics of interest and we send it only to those users who have requested it. Users can stop receiving these Alerts by going to the Mondaq News Alerts page and deselecting all interest areas. In the same way users can amend their personal preferences to add or remove subject areas.

Cookies

A cookie is a small text file written to a user’s hard drive that contains an identifying user number. The cookies do not contain any personal information about users. We use the cookie so users do not have to log in every time they use the service and the cookie will automatically expire if you do not visit the Mondaq website (or its affiliate sites) for 12 months. We also use the cookie to personalise a user's experience of the site (for example to show information specific to a user's region). As the Mondaq sites are fully personalised and cookies are essential to its core technology the site will function unpredictably with browsers that do not support cookies - or where cookies are disabled (in these circumstances we advise you to attempt to locate the information you require elsewhere on the web). However if you are concerned about the presence of a Mondaq cookie on your machine you can also choose to expire the cookie immediately (remove it) by selecting the 'Log Off' menu option as the last thing you do when you use the site.

Some of our business partners may use cookies on our site (for example, advertisers). However, we have no access to or control over these cookies and we are not aware of any at present that do so.

Log Files

We use IP addresses to analyse trends, administer the site, track movement, and gather broad demographic information for aggregate use. IP addresses are not linked to personally identifiable information.

Links

This web site contains links to other sites. Please be aware that Mondaq (or its affiliate sites) are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of these third party sites. This privacy statement applies solely to information collected by this Web site.

Surveys & Contests

From time-to-time our site requests information from users via surveys or contests. Participation in these surveys or contests is completely voluntary and the user therefore has a choice whether or not to disclose any information requested. Information requested may include contact information (such as name and delivery address), and demographic information (such as postcode, age level). Contact information will be used to notify the winners and award prizes. Survey information will be used for purposes of monitoring or improving the functionality of the site.

Mail-A-Friend

If a user elects to use our referral service for informing a friend about our site, we ask them for the friend’s name and email address. Mondaq stores this information and may contact the friend to invite them to register with Mondaq, but they will not be contacted more than once. The friend may contact Mondaq to request the removal of this information from our database.

Security

This website takes every reasonable precaution to protect our users’ information. When users submit sensitive information via the website, your information is protected using firewalls and other security technology. If you have any questions about the security at our website, you can send an email to webmaster@mondaq.com.

Correcting/Updating Personal Information

If a user’s personally identifiable information changes (such as postcode), or if a user no longer desires our service, we will endeavour to provide a way to correct, update or remove that user’s personal data provided to us. This can usually be done at the “Your Profile” page or by sending an email to EditorialAdvisor@mondaq.com.

Notification of Changes

If we decide to change our Terms & Conditions or Privacy Policy, we will post those changes on our site so our users are always aware of what information we collect, how we use it, and under what circumstances, if any, we disclose it. If at any point we decide to use personally identifiable information in a manner different from that stated at the time it was collected, we will notify users by way of an email. Users will have a choice as to whether or not we use their information in this different manner. We will use information in accordance with the privacy policy under which the information was collected.

How to contact Mondaq

You can contact us with comments or queries at enquiries@mondaq.com.

If for some reason you believe Mondaq Ltd. has not adhered to these principles, please notify us by e-mail at problems@mondaq.com and we will use commercially reasonable efforts to determine and correct the problem promptly.